On the morning of October 13, Comrade Quach Tat Liem — Member of the Provincial Party Committee and Vice Chairman of the Provincial People’s Committee — inspected the progress of 3 transport projects using central budget capital in the Vinh Phuc area, comprising: Tho Tang – Vinh Son – Thuong Trung Road, inter-commune road from Thuong Trung – Tuan Chinh Road to the Tam Phuc village gate junction, and Cao Dai – Tan Phu – Tho Tang – Lung Hoa inter-commune road. Accompanying him were leaders of several departments and sectors.

Vice Chairman of the Provincial People’s Committee Quach Tat Liem inspecting the progress of the Tho Tang – Vinh Son – Thuong Trung Road Project.
According to reports from the Vinh Phuc Area Project Management Board, the Tho Tang – Vinh Son – Thuong Trung Road Project carries a total investment of 350 billion VND. To date, site clearance work has only reached 1.74 out of 2.73 km; contractors are executing construction on handed-over site sections. Delays in issuing land unit prices and completing support procedures, alongside rising material costs and heavy rainfall, have impacted project progress.
Regarding the Inter-commune Road Project from Thuong Trung – Tuan Chinh Road to the Tam Phuc village gate junction, site clearance reached 99.9%, with completed construction volume valued at approximately 41 billion VND. The project faces lingering obstacles in compensation schemes for 8 households; construction through pond and lake areas encounters difficulties due to terrain and weather conditions. Notably, Expansion Bridge Item No. 2 cannot be deployed yet due to incomplete construction licensing procedures.

Vice Chairman of the Provincial People’s Committee Quach Tat Liem inspecting progress on the Cao Dai – Tan Phu – Tho Tang – Lung Hoa Inter-commune Road Project.
The Cao Dai – Tan Phu – Tho Tang – Lung Hoa Inter-commune Road Project carries a total investment of 150 billion VND, spanning a route length of approximately 3.4 km. As of October 2, 2026, Vinh Thanh commune basically completed site clearance and handed over the site to the project owner. However, due to a prolonged lack of site availability, construction progress was interrupted; executed volume has only reached approximately 1.1 km. The contractor is coordinating with local residents to address emerging issues around pond and lake areas to resume construction operations.
Inspecting project sites, Vice Chairman Quach Tat Liem requested the Vinh Phuc Area Project Management Board to review the overall progress of each project, holding weekly briefings with contractors to urge accelerated construction and ensure the above projects are completed within 2026.
On the basis of handed-over sites, contractors must concentrate personnel, machinery, and equipment, organizing rational construction schedules to take advantage of favorable weather conditions while ensuring work quality and occupational safety.
For site clearance work, the Vice Chairman requested local authorities, particularly Tho Tang commune, to concentrate efforts on completing site clearance within October 2026.
Relevant departments and sectors shall proactively coordinate with the project owner and local authorities to remove bottlenecks within their authority; guiding procedure completion for items not yet eligible for construction, especially Expansion Bridge Item No. 2 under the Thuong Trung – Tuan Chinh road project. Matters exceeding authority must be synthesized and reported to the Provincial People’s Committee for timely consideration and resolution.
Thuy Huong
baophutho.vn On the afternoon of November 5, the Provincial People's Committee organized a online specialized conference to evaluate progress and results in...
baophutho.vn On the morning of November 5, Comrade Quach Tat Liem — Member of the Provincial Party Committee and Vice Chairman of the Provincial People's...
baophutho.vn On November 4, Comrade Tran Viet Cuong — Member of the Standing Committee of the Provincial Party Committee and Director of the Department of...
baophutho.vn Entering the final months of 2026, the business community across Phu Tho province is concentrating resources, stepping up labor and production...
baophutho.vn As of the end of September, Phu Tho attracted over 2.4 billion USD in FDI capital, exceeding its annual plan. Behind these results lie efforts...
baophutho.vn During the first 10 months of 2026, the total retail sales of goods and consumer service revenue in Phu Tho province reached an estimated 144.9...
baophutho.vn Import-export activities across the province continue to maintain a positive growth momentum. Notably, export turnover surpassed the annual...
baophutho.vn On the afternoon of October 28, Comrade Bui Duc Hinh — Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial...
baophutho.vn On the afternoon of October 27, Comrade Phung Thi Kim Nga — Member of the Provincial Party Committee and Vice Chairwoman of the Provincial...
baophutho.vn On October 27, the working delegation of the Chungcheongbuk Provincial Council (South Korea) led by Mr. Lee Sang Sik, Chairman of the...