On the afternoon of November 12, Vice Chairman of the Provincial People’s Committee (PPC) Vu Viet Van inspected the progress of the following projects: The Project on renovation and upgrade of provincial road 310C, section from national Highway 2C to 2B; the Project of parallel road of Hanoi - Lao Cai railway (Northern route), section from Khai Quang Industrial Park (IP) to the 36m Road of Binh Xuyen IP to Ba Thien IP; and the East-West axis road of Vinh Phuc urban area, Section from Tan Phong to Trung Nguyen.

Vice Chairman of the Provincial People’s Committee Vu Viet Van inspected the Project on renovation and upgrade of provincial road 310C, Section from national Highway 2C to 2B
The Project on renovation and upgrade of provincial road 310C, Section from national Highway 2C to 2B has a total investment of nearly 438 billion VND in the period from March 2021 to December 2026. To date, the allocated capital is 307.5 billion VND, with a disbursement value reaching 278.7 billion VND. Specifically in 2025, disbursement reached 33.8/62.5 billion VND, equivalent to over 54% of the plan. Currently, the project has recovered and compensated for site clearance on 4.8/7.8 hectares, achieving 61% of the plan; construction has been executed for 3.2/5.8 km with the total completed volume value reaching 266.7 billion VND.
The East-West axis road of Vinh Phuc urban area, Section from Tan Phong to Trung Nguyen has a total investment of 258.3 billion VND, scheduled for implementation from 2019 until the end of 2025. However, the site clearance and compensation work is currently facing many difficulties. The total capital allocated to the project is 150.9 billion VND; the capital plan for 2025 is 33.4 billion VND. To date, the value of the completed construction volume is 64.1 billion VND.
The Project of parallel road of Hanoi - Lao Cai railway (Northern route), section from Khai Quang Industrial Park (IP) to the 36m Road of Binh Xuyen IP to Ba Thien IP has a total investment of nearly 679 billion VND until the end of 2026. To date, only 1.6/5.1 km, or 32.4% of the site clearance has been handed over. The completed construction volume reached 97.8/427.1 billion VND. The total allocated capital for the project is 237.2 billion VND, including a 2025 plan of 40 billion VND. The value of payments made to date is 216.3 billion VND; the disbursement for the 2025 capital plan is nearly 20 billion VND. The expected full-year disbursement is 40 billion VND, achieving 100% of the plan.
Emphasizing the pivotal role of key transport projects, Vice Chairman of the PPC Vu Viet Van requested relevant departments, sectors, and localities to focus and flexibly address bottlenecks, especially in compensation and site clearance.
The Vice Chairman of the PPC asked localities to urgently complete procedures related to compensation, support, and resettlement, to promptly hand over a clear site to the investors. Concurrently, he directed specialized agencies to proactively resolve difficulties in exploiting embankment soil and propose suitable mechanisms to secure the material supply, thereby accelerating the construction progress of the projects.
Tran Tinh
baophutho.vn baophutho.vn – In the afternoon of November 5, a working delegation of the Provincial People’s Committee led by Comrade Tran Duy Dong – Deputy...
baophutho.vn On the morning of October 31, Mr. Tran Duy Dong – Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People’s...
baophutho.vn On the afternoon of October 28, 2025, the Phu Tho Provincial People’s Committee held the 2025 Conference on Engagement with Korean Agencies,...
The 15th National Assembly, during its 10th session on October 25, approved the appointment of two Deputy Prime Ministers and three ministers for the 2021-2026 term, alongside...
Tran Cam Tu, Politburo member and Permanent Member of the Communist Party of Viet Nam Central Committee’s Secretariat, on October 24 presided over a meeting of the...
baophutho.vn On the afternoon of October 24, 2025 (local time), in Sofia, the capital of Bulgaria, a Memorandum of Understanding (MoU) on friendship...
baophutho.vn On the morning of October 22, the Agriculture and Environment Magazine (under the Ministry of Agriculture and Environment) coordinated with...
baophutho.vn On the afternoon of October 17, the Standing Committee of the Phu Tho Provincial Party Committee held a meeting with female leaders on the...
baophutho.vn On the evening of October 14, Thang Long Vinh Phuc Industrial Park Co., Ltd. held a ceremony to celebrate its 10th anniversary.
baophutho.vn Just over a month after the establishment of the Democratic Republic of Vietnam, on October 13, 1945, President Ho Chi Minh sent a letter to...