On December 18, Mr. Vu Viet Van, Member of the Standing Committee of the Provincial Party Committee and Vice Chairman of the Provincial People’s Committee inspects several key projects in the Vinh Phuc area.
Vice Chairman Vu Viet Van directs the acceleration of compensation and site clearance for the Yen Lac - Dragon City Urban Area Project.
The Yen Lac - Dragon City Urban Area Project currently has 150 households who have not yet agreed to asset inventory or compensation with a total of approximately 8.7 hectares.
After hearing the report, Vice Chairman Vu Viet Van requested local authorities and relevant departments to focus on resolving these bottlenecks. He emphasized the need to enhance communication to gain public consensus, striving to hand over “clean land” to the investor by the first quarter of 2026.
The investor was urged to proactively cooperate with local authorities on compensation and site clearance, adopting a “clear-as-you-go” construction approach to ensure the project stays on schedule.

Vice Chairman Vu Viet Van inspects the construction site of Ring Road 3 (Yen Lac - Binh Duong section) under the Provincial Transport Development Plan.
Regarding key transport projects, including Ring Road 3 (Yen Lac - Binh Duong section), the Parallel Road with Hanoi - Lao Cai Railway (from Hop Thinh - Dao Tu road to the Vinh Yen bus station intersection), and the Tay Thien - Tam Son Road (sections from Tay Thien to Hop Ly Bridge and from National Highway 2C to Van Truc Lake), site clearance currently faces difficulties related to land and asset valuation and resettlement arrangements. Additionally, the rising costs of construction materials—particularly fill dirt and sand—along with challenges in arranging storage sites and waste disposal areas, have impacted construction progress.
Highlighting the pivotal role of these key transport projects in the province’s socio-economic development, Vice Chairman Vu Viet Van demanded that departments, sectors, and localities be proactive in troubleshooting.
He also directed the urgent completion of compensation, support, and resettlement procedures to hand over clean sites to investors as soon as possible. Specialized agencies must proactively address difficulties in sourcing fill dirt and propose appropriate mechanisms to ensure the supply of construction materials, thereby accelerating project progress and contributing to local socio-economic growth.
Dang Thuong
baophutho.vn In the final months of 2025, the production and business atmosphere across industrial parks and clusters in the province is vibrant. Many...
baophutho.vn Located at the gateway of Phu Tho province and bordering the capital city of Hanoi, the Khai Quang Industrial Park (IP) in Vinh Phuc...
baophutho.vn On December 16th, a working delegation led by Standing Deputy Secretary of the Provincial Party Committee Bui Van Quang to inspect the...
baophutho.vn In the context of rapidly changing global economics and increasingly deep integration, the business community in the province is proactively...
baophutho.vn With a favorable geographical location, modern transport infrastructure, an abundant human resource, and an open, transparent investment...
baophutho.vn Recognizing the development of Industrial Parks (IPs) as a key driving force to promote economic growth, shift labor structure, and create...
baophutho.vn After the merger, Phu Tho province with a scale of over 9,361 square kilometers and a population of more than 4 million, has become the...
baophutho.vn The year-end is the golden time for enterprises to accelerate, make a breakthrough towards the finish line, concentrate all resources to strive...
baophutho.vn On the morning of December 8th, Mr. Tran Duy Dong – Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's...
baophutho.vn Entering the beginning of December, the atmosphere of harvesting Nam Son ancient tangerines in Van Son commune becomes more bustling than...