On the morning of April 1, Mr. Quach Tat Liem – Member of the Provincial Party Committee and Vice Chairman of the Provincial People’s Committee – chaired a meeting to hear investors and localities report on the progress of site clearance and construction of several transport projects in the Vinh Phuc area.

Vice Chairman Quach Tat Liem speaking at the conclusion of the conference.
At the conference, the Vinh Phuc Regional Project Management Board reported on the implementation progress of three key transport projects:
National Highway 2 Expansion (Vinh Yen - Viet Tri section): This site clearance sub-project has a total investment of over 556.3 billion VND, implemented from 2024 to 2027. Approximately 1,223 households are affected, with a recovery area of about 22.46 hectares. To date, Te Lo and Vinh Thanh communes have achieved nearly 98% site clearance. However, Vinh An and Vinh Hung communes still face difficulties in identifying land origins, assets on land, land overlaps, and implementing resettlement and relocation of technical infrastructure.
Capital Region Connection Infrastructure Project: This includes Ring Road 5 of the Capital Region and the section along the foot of Tam Dao mountain (connecting Ring Road 5 with National Highway 2B to Tay Thien, toward National Highway 2C and Tuyen Quang). The project has a total investment of 1,800 billion VND and a length of 26.7km. Since its commencement in February 2022, 1,028 billion VND has been disbursed (65.5%). Site clearance has reached 60% (about 15/25km). Remaining areas are stalled due to issues with land origins, forestry land, material sources, waste disposal sites, and infrastructure relocation procedures.
Route from DT.310B to Route D3 (Thanh Lanh village, Trung My commune): This sub-project (Component 1 - Site Clearance) has an investment of 108.9 billion VND, a length of 6.5km, and an occupied area of 19.17 hectares. Currently, specialized agencies have identified owners for 18.1 hectares. It is expected that land origin verification will be completed in May-June 2026, with compensation plans and site handover scheduled for the second half of 2026.
Concluding the meeting, Vice Chairman Quach Tat Liem emphasized that completing site clearance is vital to accelerating key transport projects, increasing public investment disbursement, and driving socio-economic development to achieve double-digit growth targets.
The Vice Chairman requested local authorities to mobilize the entire political system, assign clear responsibilities, and step up communication to gain public consensus. He assigned the Department of Agriculture and Environment to lead and coordinate with relevant departments to provide specific guidance on compensation value determination for technical infrastructure. For persistent obstacles, units must compile reports for the Provincial People’s Committee to provide timely directions, ensuring “clean sites” are handed over to construction units on schedule.
Duc Anh
baophutho.vn Entering the 2026-2030 period, the province is not only targeting an annual GRDP growth of 11%-12%, but is also focusing on redesigning its...
baophutho.vn In the vibrant development rhythm of the Northern Midlands and Mountains, Phu Tho is emerging as an industrial bright spot with powerful...
baophutho.vn As April arrives, the land of Phu Tho is not only filled with the sacred atmosphere of the Ancestral Anniversary but also pulsating with the...
baophutho.vn Identifying infrastructure development as a top priority, the province is focusing on drastic measures to remove bottlenecks, shorten...
baophutho.vn As 2026 marks the inaugural year for implementing the Resolution of the 14th National Party Congress and the Socio-Economic Development Plan...
baophutho.vn On the afternoon of April 23, Mr. Tran Duy Dong — Alternate Member of the Party Central Committee, Deputy Secretary of the Provincial Party...
baophutho.vn On the morning of April 23, under the chairmanship of Mr. Tran Duy Dong — Alternate Member of the Party Central Committee, Deputy Secretary of...
baophutho.vn Right from the early months of 2026, the economic landscape of the province has shown a distinct flourish with GRDP growth exceeding...
baophutho.vn The impressive growth figures of Q1/2026 are creating positive psychological momentum for Phu Tho province. However, behind this bright picture...
baophutho.vn Phu Tho identifies transport infrastructure as one of its strategic breakthroughs to stimulate socio-economic growth, expand developmental...