On the morning of February 9, Mr. Quach Tat Liem, Member of the Provincial Party Committee and Vice Chairman of the Provincial People’s Committee, conducted an on-site inspection of the Hoa Binh - Moc Chau Expressway Project and presented Tet gifts to workers on the construction site.

Vice Chairman Quach Tat Liem listens to the contractor’s report on the project’s progress.
To date, land clearance for the Hoa Binh - Moc Chau expressway has reached 32.8 out of 34 km, equivalent to 97%. Specifically, some sections in Da Bac and Cao Son communes are still pending clearance for a few remaining households, while Tien Phong commune has achieved 100% completion. The contractor is currently coordinating with relevant units to relocate technical infrastructure, including power lines and water supply systems.
During the inspection, the Hoa Binh Regional Project Management Board proposed that the Provincial People’s Committee petition the Prime Minister for the remaining 1,005.99 billion VND of central budget capital in the 2027 plan. Additionally, they requested permission to expand the Hoa Binh - Moc Chau section (km19 - km53) from two lanes to four lanes as per the complete master plan, with an estimated additional investment of approximately 8,171 billion VND.

Vice Chairman Quach Tat Liem presents Tet gifts to workers at the Hoa Binh - Moc Chau Expressway construction site.
Speaking at the site, Vice Chairman Quach Tat Liem commended the active and urgent working spirit of the contractors and the close supervision of local authorities. He acknowledged that the project faces significant challenges due to complex terrain, geology, and prolonged rainfall. However, thanks to high responsibility and decisive leadership, the progress basically meets the requirements.
On the occasion of the Lunar New Year, the Vice Chairman visited and presented gifts to encourage the staff and workers. He emphasized: "The province aims to complete the project before December 31, 2027, one year ahead of schedule. To achieve this, contractors must continue to overcome difficulties, take advantage of dry weather, and increase shifts to accelerate progress."
Van Anh
baophutho.vn On April 14, in Beijing, Phu Tho province organized an investment promotion conference attended by a large number of delegates, businesses, and...
baophutho.vn On the afternoon of April 14, the Phu Tho Provincial Tax Department held a conference to review tax performance for the first quarter of 2026...
baophutho.vn On the morning of April 13, in Cu Dong Commune, Thanh Cong Construction and Investment Co., Ltd. held the groundbreaking ceremony for the Thang...
baophutho.vn According to the Department of Agriculture and Environment, for the 2021–2025 period, the province has focused on developing specialty pomelo...
baophutho.vn On the afternoon of April 10, the Provincial Industrial Zones Management Board held a ceremony to award the Investment Registration Certificate...
baophutho.vn On the afternoon of April 9, Mr. Vu Viet Van — Member of the Provincial Party Standing Committee and Vice Chairman of the Provincial People's...
baophutho.vn Identifying infrastructure development as a critical task, the province is focusing on decisive leadership to remove bottlenecks, shorten...
baophutho.vn In the first three months of the year, foreign direct investment (FDI) attraction in the province continued to record positive signals,...
baophutho.vn The impressive growth figures of Q1/2026 are creating positive psychological momentum for Phu Tho province. However, behind this bright picture...
baophutho.vn Digital transformation is no longer an option but an inevitable requirement across all sectors of life. For the collective economy and...